Tuesday, August 11, 2015

State Park Animal Corridor to Let in September?


Although it's pretty certain that the City of El Paso's priorities and not TxDOT nor regional engineer, Bob Bielek, are to blame, the process for actually building the wildlife corridor with a hike and bike trail at the Tom Mays Unit of the FMSP has been a lengthy one.

In a July 30, 2015 email to Rep. Joe Pickett, Bob Bielek wrote: "I discussed how we are going to fund this project with staff today and we came to the conclusion that it makes the most sense to fund the project out of Category 11, which is essentially District discretionary funds.  We will likely have enough to fund this project with FY 16 funds and should be able to let in September or October. The reason for this is that we would not need to get the project into the TIP, STIP or have to go through all of the paperwork associated with conformity, etc. Depending on final estimates this could change, but as of right now we believe this is the fastest and cleanest approach."

Let in September or October? Let's hope it's finally true.

Tuesday, June 9, 2015

Remember that FMSP Hike-Bike-Wildlife Corridor and Entrance at Tom Mays?



In March TxDOT presented a report to City Council that included the hiking/biking/animal corridor into the Tom Mays unit of the Franklin Mountains State Park. The corridor is the key connection between the north and south sides of the State Park west of the mountains. It sounded like good news. But where are we now?

On April 7th of this year in an email, TxDOT District Engineer, Bob Bielek, said that he would like to accelerate the project and start sometime in the first quarter of the next fiscal year. (It begins in September 2015.) Acceleration is necessary because of all of the work beginning on I-10 from downtown to Executive. More demand will be put on Loop 375 (the Transmountain Highway.) 

In an email on the same day, Bielek stated that TxDOT workers pick up about 4 dead deer in a year and about 4 dead smaller animals a month. He didn't think that the death toll was too high. His opinion, of course; and the opinions of wildlife experts don't register with him or TxDOT.

Now let's review the record of broken promises and shifting predictions. Judy Ackerman passed some detailed notes about the corridor/connectivity project to me. Her notes begin in January 2013.

January 24, 2013 - the Texas Parks and Wildlife Commission considers a proposed transfer of 8 acres of park land to TxDOT for the purpose of a new entrance into the Tom Mays Unit.

November 19, 2013 - at the Border Highway East Public meeting, Bielek stated in a conversation that Dr. Rick Bonart's idea for an animal crossing was a good one , that the project might cost $2 Million, and that TxDOT might start working on it in the Fall of 2014.

December 11, 2013 - plan unveiled to public and is warmly received.

April 10, 2013 - TxDOT holds a public meeting about the corridor/connection/new park entrance. Plans get a positive response.

April 15, 2013 - at a special meeting of the Metropolitan Planning Organization (MPO), Transportation Policy Board (TPB), Bob Bielek announces that he is committed to the project in 2014.

February 20, 2014 - at an El Paso League of Women Voters meeting, Bielek gives a Fall 2014 date for the beginning of a corridor between the north and south portions of the park that have lost direct access. He gives a date of Fall 2014 for the beginning of such a project.

April 11, 2014 - at a breakfast meeting sponsored by NE El Paso City Council Representative, Carl Robinson, Bielek says that the project will begin in Fall 2014, take 3 months and cost $1 Million.

October 3, 2014 - Bielek says that the project is still in design.

March 17, 2015 - in a presentation to City Council it is announced that the project will cost $3 Million and that the estimated let date is 2016.

May 15, 2015 - again at a Carl Robinson breakfast, Bielek announces that the project will let in 2 to 3 months and that funding will be from Proposition 1 Funds. (Previously it had been from his discretionary account and then "Denial of Access" funds.)

As you can see, dates keep moving up, estimated costs keep changing as well as funding sources. It's June 2015, when will this corridor, which should have begun in Fall of 2014, really begin - if at all?

Thursday, August 14, 2014

Bielek Backpedaling on State Park Entrance?

TxDOT Regional Engineer, Bob Bielek, appears to be backpedaling on his promises about a Franklin Mountains State Park entrance. A plan to connect the southern and northern sides of the park dissected by Transmountain Road was set to begin this fall. On April 11, 2014 at City Council Rep. Carl Robinson's breakfast meeting, Bielek said regarding the connectivity project: "Expect to start in Fall 2014.  Will take 3 – 4 months to complete.  Not a difficult project, because it is a short-span bridge.  Costs a bit over $1,000,000." His statement was not much different from what he indicated in November of last year to a group of park advocates prior to a public meeting in December. Bielek told the public that his discretionary funds would pay for the project.

Now Bielek is saying, as elpasonaturally has learned, that the project might begin in January and that he is looking for money for it.

The plan called for a new park entrance with a corridor under the Transmountain highway for animals, mountain bicyclists, hikers and other pedestrians. Conceptual drawings may be viewed at this post. The TxDOT page of the drawings is not loading well currently.

It seems that Bielek is backpedaling on the project which suggests that he was never serious about it before. "He often tells people what they want to hear," one observer mentioned. 

What's next? Perhaps like so many public projects the actual start date is actually much later than originally estimated. It may be prudent to wait until December to see what, if anything, happens. If nothing, then it will be obvious that once again TxDOT has been less than honest with Texas citizens they are supposed to be serving.

Thursday, January 9, 2014

O'Rourke Gives Strong Support to FMSP Connectivity Proposal

In a letter to a TxDOT official, Congressman Beto O'Rourke supports the most recent entrance proposal because it offers safety and connectivity. He applauds TxDOT for working with "the community, environmental groups, and Texas Parks and Wildlife Department". 

Here is his letter:

Click to enlarge.

Friday, December 13, 2013

See TxDOT Drawings of State Park Connectivity Project

TxDOT has published drawings of the connectivity project at the entrance to the Franklin Mountain State Park HERE.

Email and Facebook posts continue to be hugely positive. The only question seems to be whether there is a way to move the project along faster. I got this email from Terri Garcia's favorite EX-PSB member:

"One of the things that doesn't compute is not being able to use discretionary funds to build this feature ( either in whole or part ). After all, what monies were used to build the wildlife tunnel between Paseo and Plexxar?

"Why is there a distinction?

"I really like the design, it's very thoughtful, and needs to be expedited or risk being shelved.

"I'm glad the current Transmountain project is ahead of schedule, so any delays caused by doing this now probably would have little net effect on that benchmark.

"The public was promised by TxDOT, as a condition of approval by City Council to not only  look at but resolve these issues.

"TxDOT just issued a $3.5M change order at the City's request for cosmetic enhancements. If that's doable, then $1.5M for functional and safety improvements should not only be possible but a priority.

"Finally, this project is one of only a handful at most through out the entire country. It's a huge PR opportunity!"

Bob Bielek did say the other evening that the "cosmetic enhancements" were done at the request of the City. 

It's always good to see City leadership get their priorities straight.


Thursday, December 12, 2013

Environmental Community Gives Thumbs Up with TxDOT Park Entrance Plan

Last evening at Canutillo High School, Regional Engineer Bob Bielek and his staff unveiled their plan for the new park entrance at the Tom Mays Unit of the Franklin Mountains State Park. You can review the plan on one of my previous blog posts HERE. The plan met with enthusiasm from a small but happy sample of the local outdoors, environmental/conservation, recreation and Master Naturalists community. Almost as soon as the meeting ended last evening the chatter on Facebook began and it is all positive.

During the first thirty minutes of the gathering, people reviewed pictures of the proposed underpass for hikers, bicyclists and animals as well as pictures of the entry and egress configurations for the park. There were a number of TxDOT and design engineers on hand to answer questions. Bielek also was on hand to answer questions and visit. He then informally addressed the gathering and explained safety and wildlife issues and park access issues. 

The point that I really want to make here is how comfortable the situation was. Two years ago the scene was totally different. Former Engineer Chuck Berry of TxDOT had plans and wasn't willing to listen. I remember well that as person after person came to the mike to speak about the need for connectivity between the two sides of the park, a workable animal corridor, etc., etc., Chuck and company sat at front and chatted among themselves. They weren't listening. Not only did Bielek's plans show that they listened and listened to wildlife experts such as Dr. Cesar Mendez and Lois Balin, but that they heard from hikers and mountain bikers and did their homework on safety issues.

Bielek discussed the traffic issues and satisfied the group assembled that a left turn into the park going east on Transmountain would still be safe whereas a left out of the park to go east would not be as safe as requiring a U-Turn of sorts. That U-turn (a right out of the park going west and a U-Turn at Resler) is not the perfect solution - but it sure is safer and it saves the park entrance from having an enormous scar of a concrete and asphalt entryway. The simple U-Turn versus an enormous exchange is, obviously, cheaper.

Bielek also explained the need to go after Denial of Access funds. The modificaitons at the entry are really not transportation issues but right of way issues. There is funding for ROW work and that is separate from the discretionary funds that he seemed to think would work earlier. The cost will be $1.5-2 Million. Some of the local politicians on hand seemed to think that there might be a way to get funding sooner than later. Whatever, Bielek now projects that the project can be done in 15 to 18 months from today or March to June 2015. 

Because of our previous experience with TxDOT and the former Engineer, it has been easy to expect the same level of duplicity and arrogance from Bielek. Bielek is a guy who likes to wear cowboy boots, visit with folks, get feedback while at the same time possessing the maddening trait that comes from believing that we are all subject to the laws of the Universe, Nature, physics, what have you. He's not a person who cares so much about policy. He's the kind of person who takes current policy as a given in the equation. Basically it is "here is what I can do for you folks - what we can do based on natural law and what the laws of the land will currently let me do." When at first he said that discretionary funds would do the trick, he wasn't trying to deceive just trying to figure out how it could work for the folks he serves.

The plans unveiled last night and the informal straight-talk of the Regional Engineer went a long way to heal a very fractured relationship between conservationists along with outdoors recreationalists and TxDOT here in El Paso. There are still serious institutional issues and there will always be that struggle for balance between environmental and economic values. But one thing is for sure - Bielek's TxDOT office knows what a real animal corridor looks like and knows that people enjoy hiking and bicycling in our beautiful Franklin Mountains. Now if we can just do something to convince them to be a bit more pro-bicycle . . . 

By the way, your comments are needed. At issue is what most of us have been saying all along: We need connectivity. The Transmountain expansion has cut off access between the two sides of the park. Hikers, bicyclists and animals need safe, attractive corridors. Right of way to the park must be safe. This plan does it. Email your comments to ELP-FMSParkEntrance@txdot.gov. If you prefer snail mail - okay - here it is:

Blanton & Associates
Attn: Connectivity at the Franklin Mountains State Park
5 Lakeway Centre Court
Suite 200 
Austin, TX 78734

Wednesday, November 6, 2013

Breaking News: Public Meeting for FMSP Entrance Scheduled for December

The office of State Representative Joe Pickett received a note from TxDOT this afternoon.  A public meeting about the entrance to the Tom Mays Unit of the Franklin Mountains State Park is scheduled for Canutillo High School, from 6 to 8 PM, on Wednesday December 11th.

Thursday, July 18, 2013

State Park Entrances and Dead Birds

I'm not sure what the title of this post should be. "Point/Counterpoint".  "Maybe Bielek Was Right and I Owe Him an Apology".  Or "Franklin Mountains Wilderness Coalition Fiddles While . . . "  Read on.  It's lengthy but please read on.